Why how you procure MMC matters as much as whether you use it
The social housing sector is building at a pace it hasn’t seen in a decade. In England, housing association starts for social rent jumped 57% in 2025/26, completions were up 49%, and with £39bn committed through the new Social and Affordable Homes Programme, the pipeline ahead is substantial. MMC is expected to play a growing role in delivering that pipeline. Barbour ABI estimates the MMC market will reach £800m by 2029, and a survey by the NHF and Building Better found housing associations are planning over 30,000 MMC homes by 2028. The approach to MMC procurement will shape whether those homes are delivered well.
That’s a lot of homes being procured in ways that many housing associations haven’t done before, or have only done once or twice. And the procurement approach makes a bigger difference to whether an MMC scheme succeeds than most development teams realise.
Tony Woods, Technical Manager at PfH, put it well at PfH Live 2026 during a panel discussion hosted by the Building Better Community of Practice. Too often, he said, people treat procurement as something that happens at the end of the process, trying to get a square peg into a round hole. The projects that work are the ones where procurement moves to the front, where the supply chain is engaged early enough to actually shape the scheme rather than just deliver it.
That principle applies to traditional construction too, but with MMC it’s even more important, because the manufacturing process imposes constraints and opportunities that conventional procurement approaches aren’t designed to handle.
The failures have shaped the conversation, and that’s partly the problem
The past few years have been rough for MMC’s reputation. TopHat, ilke Homes, Modulous: a string of high-profile collapses has left some boards and development directors understandably cautious. If your only reference point for offsite construction is a manufacturer that went into administration halfway through a scheme, it’s hard to build enthusiasm for another go.
But the picture is more complicated than the headlines suggest. At the PfH Live 2026 panel, Mark Marsh from Raven Housing Trust talked about a project where exactly that happened: the original contractor went into administration, and despite everything, the finished scheme became one of their strongest examples of what MMC can deliver. The lesson wasn’t that MMC is risky. It was that understanding the manufacturing process, planning properly for groundwork and site conditions, and making sure the trades working around the modules know how the system fits together are the things that determine the outcome.
As Mark put it, it’s not rocket science. It’s timber frame built in a factory, wrapped in steel, put on a lorry and delivered to site. The same wiring, the same plasterboard. What makes the difference is quality assurance, consistency of delivery, and accepting that it still gets muddy on the field outside.
The sector needs to have honest conversations about what different MMC systems can and can’t do, rather than treating the whole category as either the answer to everything or something to avoid entirely.
Why procurement has to come first, not last
With traditional construction, there’s a well-worn sequence. You design the scheme, get planning consent, then go to market to find a contractor. It’s imperfect but familiar, and most procurement teams know how to run it.
MMC doesn’t work like that. The manufacturing process needs to influence the design from the start, because factory-built components have tolerances, dimensions, and sequencing requirements that can’t be retrofitted into a scheme that was designed without them in mind. If the manufacturer isn’t involved until after planning, you end up redesigning at cost, or compromising on the very efficiencies that made MMC attractive in the first place.
This is where Christie Edge from Modular Wise (Places for People) grounded the PfH Live 2026 discussion in something fundamental. Everything should be designed around the people who will actually live in these homes, she argued. From good design, the speed, consistency and quality follow. But that design process needs to include the supply chain from the outset, which means procurement needs to facilitate that early engagement rather than gatekeep it.
Lewis Tolputt from Classic Builders reinforced this from the contractor’s side. Being transparent and bringing people on board early, he said, delivers benefits that are hard to believe until you’ve seen them. His firm has been advising housing associations before the planning stage, helping them think through the whole life cycle of the building rather than just the construction phase. That kind of collaboration doesn’t happen through a conventional competitive tender issued after designs are fixed.
What good procurement looks like for MMC
There are a few things that consistently separate schemes that go well from ones that don’t, and most of them come down to how the procurement was set up.
Engaging the supply chain before you’ve locked the design. This sounds obvious when you write it down, but it runs against the grain of how most housing associations procure. The instinct is to get the design as far advanced as possible before going to market, because that feels like it reduces risk. With MMC, it actually increases it, because you lose the opportunity for the manufacturer to optimise the design for their production process. The schemes that work best tend to be the ones where there’s a genuine dialogue between the client, the architect and the manufacturer early enough that the design reflects how the building will actually be made.
Understanding that MMC is part of the offering, not the whole offering. One of the clearest takeaways from the PfH Live 2026 panel was that MMC won’t replace traditional construction. A mix is needed. Some elements of almost every scheme, groundworks, external landscaping, interfacing trades- will be delivered traditionally even when the superstructure is built offsite. The procurement approach has to accommodate that, which is why PfH’s Integrated Traditional Build and MMC framework was designed the way it was: with trusted local contractors leading MMC projects and delivering the traditional elements alongside them, based on feedback from housing associations about what they actually needed.
Educating the whole project team, not just the procurement function. One of the recurring themes from organisations that have delivered successful MMC schemes is how much effort goes into making sure everyone on site understands the system. Trades that are used to working with brick and block need to understand how a modular or panelised system goes together, where the tolerances are, and what they can and can’t modify on site. This isn’t procurement’s job in isolation, but procurement can build it into the contract from the start, making induction, training and interface management an explicit requirement rather than something that gets figured out on the fly.
Due diligence that goes beyond the balance sheet. Given the manufacturer failures the sector has experienced, due diligence on MMC suppliers needs to look at more than financial standing. It needs to assess manufacturing capacity, the quality management system in the factory, the firm’s track record on similar projects, their warranty arrangements, and how they handle the interface between factory production and site delivery. PfH runs independent due diligence checks on all suppliers appointed to its frameworks, which is one of the reasons members use them: it takes that burden off the development team.
MMC and net zero are increasingly in the same conversation
One thing that came through strongly from the PfH Live 2026 panel, and that we’re hearing more and more from members, is that MMC and energy performance are becoming inseparable. Lewis Tolputt spoke about Passivhaus schemes where MMC is integral to achieving the standard, not just because of the precision and tighter tolerances you get from building in a factory, but because of the skills and consistency that a controlled manufacturing environment makes possible.
For housing associations in England working towards the Future Homes Standard, and for any housing association with its own net zero commitments, this matters. Building fabric performance depends on getting hundreds of small details right: continuous insulation, airtight membranes, thermal bridge details around windows and junctions. Doing that consistently on a traditional building site, in typical British weather, with different subcontractors on each plot, is hard. Doing it in a factory where the same team builds the same details every day is considerably more reliable.
The procurement implication is that when you’re specifying MMC, the energy performance conversation should be part of the specification from day one, not bolted on after the manufacturing approach has been decided. The two need to be designed together.
What’s different in Wales
Most of what the panel discussed applies on both sides of the border, but Welsh members are working within a different policy and funding picture. New social homes in Wales are funded mainly through the Welsh Government’s Social Housing Grant rather than the Social and Affordable Homes Programme, and every new build home funded by the grant must meet the Welsh Development Quality Requirements 2021 (WDQR 2021). The Welsh Government’s MMC strategy for social housing set out to make sure MMC is considered as a potential delivery route for every social housing development it funds. For many Welsh members, the question is less whether to consider MMC and more how to procure it well.
Energy standards differ too. The Future Homes Standard applies in England, while Wales sets its own requirements through Part L of the Welsh Building Regulations. The Welsh Government consulted on a Part L 2025 standard in 2025, and its preferred option for new homes was broadly aligned with England’s Future Homes Standard. Whichever standard applies, the point about designing energy performance in from day one holds.
Welsh members procure under the Procurement Act 2023 alongside the Procurement (Wales) Regulations 2024, and the Social Partnership and Public Procurement (Wales) Act 2023 sets out socially responsible procurement duties for the organisations it covers. Early market engagement and clear social value requirements sit comfortably with both, which supports bringing procurement in at the start of an MMC scheme.
The pipeline is there. The question is whether procurement keeps up.
In England, with the government’s commitment to the largest council housebuilding programme since the postwar era and £39bn flowing through the Social and Affordable Homes Programme, the volume of homes the sector needs to deliver over the next decade is clear. MMC will be part of how that volume gets delivered. Not the only part, but an increasingly important one.
The housing associations that get the most from it will be the ones that treat procurement as the front door to the project rather than a hurdle to clear on the way through. Early engagement, honest conversations about what each system can deliver, proper due diligence, and contracts that are set up for collaboration rather than adversarial risk transfer. None of that is complicated, but all of it requires procurement to be involved from the start.
Tony Woods is Technical Manager at Procurement for Housing (PfH).
This article draws on a panel discussion at PfH Live 2026, chaired by Katie Rudin of the Building Better Community of Practice.
How PfH can help
The MMC schemes that go well have procurement involved from the start, with the supply chain engaged early and due diligence that goes beyond the balance sheet. Our frameworks and DPS give members compliant routes to the contractors and manufacturers who can work that way, and our consultancy team can support you if you’re exploring MMC for the first time.
Modern Methods of Construction (Category 1) framework. Gives housing associations access to offsite volumetric home manufacturing through direct award, covering houses, apartments and extra care up to 18m. Developed in partnership with Building Better.
Integrated Traditional Build and MMC framework. Connects you with 22 appointed contractors who can lead MMC projects while delivering traditional elements alongside them, across 10 regions of England and Wales.
MMC Category 2 DPS. Provides access to panelised and non-volumetric MMC manufacturers, with new suppliers able to join throughout the life of the DPS.
Procurement support. Independent due diligence on MMC suppliers, specification development and procurement strategy for housing associations exploring MMC for the first time.

About Tony Woods
Tony Woods is a construction and procurement specialist with more than 30 years’ experience across the building, certification, and public sector framework sectors.
Currently Technical Manager at Procurement for Housing, Tony is responsible for supporting the development and delivery of compliant procurement frameworks that enable housing providers and public sector organisations to access high-quality construction and refurbishment solutions. He previously spent nearly a decade as Technical Manager at LHC Procurement Group, where he led the technical development and procurement of pre-tendered frameworks covering offsite housing, modular buildings, schools and community facilities, and energy efficiency and refurbishment programmes.
Earlier in his career, Tony held technical and business development roles with organisations including Building Research Establishment, BSI Group, and UL Solutions, where he worked on testing, certification, and the market development of innovative construction systems. He has also held technical leadership positions within the offsite housing sector, supporting the compliance of timber and modular systems with UK regulations and sustainability standards.
With deep expertise in offsite construction, technical compliance, and framework procurement, Tony brings extensive industry knowledge to the development of robust procurement routes that support housing delivery, modern methods of construction, and sustainable building solutions across the UK.
Sources:
National Housing Federation, NHF supply figures show record boost in new social homes, July 2026. https://specificationonline.co.uk/articles/2026-07-14/nhf-supply-figures-show-record-boost-in-new-social-homes
pbctoday, Social housing could be key to offsite manufacturing rebound (Barbour ABI forecast), February 2026. https://www.pbctoday.co.uk/news/mmc-news/social-housing-could-be-key-to-offsite-manufacturing-rebound/159226
National Housing Federation and Building Better, State of MMC Delivery in Social Housing survey, reported by Inside Housing, February 2026. https://www.insidehousing.co.uk/home/researchers-predict-social-housing-driven-boom-in-mmc-with-market-expected-to-hit-880m-by-2029-95869
Inside Housing, Traditional builders sign up to £800m MMC framework. https://www.insidehousing.co.uk/home/traditional-builders-sign-up-to-800m-mmc-framework-88526
Welsh Government, Welsh Development Quality Requirements (WDQR) 2021: integrated impact assessment, May 2025. https://www.gov.wales/welsh-development-quality-requirements-wdqr-2021-integrated-impact-assessment
Welsh Government, Re-imagining social house building in Wales: a Modern Methods of Construction strategy for social housing, implementation plan, February 2021. https://www.gov.wales/sites/default/files/publications/2021-03/action-plan.pdf
Welsh Government, Building Regulations Part L: 2025 review, August 2025. https://www.gov.wales/building-regulations-part-l-2025-review
Social Partnership and Public Procurement (Wales) Act 2023, section 24, legislation.gov.uk. https://legislation.gov.uk/asc/2023/1/section/24/data.htm?view=plain